Small, Incremental Changes

We’ve got a thermometer set up to read in the house (ground level, north side) and the garage.  The upper temperature reading is for the garage, and the lower is inside the house.  A gradual climb in temperature from week-to-week indicates that the house is warming from the below-freezing temperatures we experienced before it was buttoned up with all the gaps sealed and insulated.

Readings are from January 4th, January 14th, and January 20th. RJStegora uses a couple of small space heaters and a dehumidifier to help with drying mudded gypsum walls and also the ongoing concrete drying.

 

Buttoning-up materials:

 

Gypsum board and joint compound may seem less exciting than concrete or framing.  We do want you to be impressed with this work:  Some of the walls are 3 stories tall – from basement to second floor ceiling. The crew which put the walls up worked fast, and the “mudder” was a lone fellow, who worked all weekend.  Insulation, taping, sealing, and glass siting are all critical parts of keeping the indoor temperature stable.

 

House and breezeway after “rocking” and “mudding;” much cleaner looking lines.

 

 

Garage has interior walls, and doors!  The interior temperature will be warmer now that the doors are on.

 

Supplies and tools

DSC_4977
Tools of the trade, empty boxes
DSC_4966
Tape. For seams.

That’s it for the  moment.  We’re looking at finishes for floors, and pulling together the details like tile and cabinets and shelves.

Getting Even More Concrete

RJStegora’s team smoothed the garage floor with sand and reinforced it with steel rebar.  Pipes were laid to help track the slope of the concrete; it needs to slope downward toward the front of the garage.  Under the slab are conduits with electric lines, one ready for the solar panel’s electricity, and water drains.

Can’t you just smell the ozone coming off the grinder as it cuts rebar?

Once the concrete was poured, the edges needed a bevel, and it is worked first with a power float (bottom photo, resting after a hard day), and then by hand. When finished, the surface will be smooth and the bubbles will have been worked out, and larger gravel and sand moved below the surface.

The garage floor was poured on a Friday, and kept above freezing over the weekend.  By Monday, it was being used for staging, and by Friday after, there was a west-end sidewalk to keep the mud at bay.

DSC_4419

Concrete cures better at warmer temperatures, giving it more time to “set.”  There are additives which can accelerate the process, but keeping it above freezing can be accomplished with low-tech methods like a clear canopy to let light and heat energy in, and space heaters can help.  Below is the canopy over the garage’s back sidewalk.

Concrete is a versatile material, and has been around at least as long as 6500 BCE.  Examples of the early use can be found in southern regions of modern day Syria and Jordan, as construction material for houses and underground, water-proof cisterns.  Much of modern concrete is Portland Cement mixed with water. A chemical reaction occurs, forming a hard matrix of durable, stone-like material.

After the garage was done, the next concrete project was the front retaining wall and steps.  The retaining wall got blankets to warm it, as it set over several days.  The step needed the plastic canopy and heat over a weekend.

 

There we have it. The concrete at the edges, and the edge of our 2017 building season.

We’ve got tons of wiring to talk about coming up soon.  All our personal advisors suggest we should make conduit or wire run into any and every potential location, including low-voltage lines for communications systems.  Oh, and the house is warming up, making it nice to work in shirtsleeves.

On a last note, here is what we’re looking forward to in the spring:  tapping the sweet maple trees for syrup. Until then, sweet winter dreams!

DSC_0090

Glass+House=Warm (Late November)

Ancient structures for living needed some fresh-air;  the English “windows” is based on the ancient word roots:  Wind-holes.

Sweet Tree Passive House has a lot of windows, especially on the south walls, letting in generous light and heat energy, and almost no air when closed.  The glass has a low iron content for better light/heat energy transferring into the house.  The windows are triple-paned, with argon between panes.  We can expect values of U-0.118 (heat loss rating) and R-8.5.  (link to definition:  http://www.efficientwindows.org/ufactor.php)

In comparison, good double-paned windows may have U ratings of 0.30; lower is better.

The weather has turned very cold in Minnesota, dropping over 30F overnight.  RJ Stegora’s construction team buttoned-up the window-to-wall gaps with a foam tube and calk.

Seeing all the steps which go into making our home a tight, functioning structure helps us to understand what finishes and lights work best in a passive house.  Some selections need adjusting now that we know more.

DSC_4286DSC_4288

This material keeps insulation up in the rafters, and moisture out of that insulation. It has about a dozen languages printed on the instructions!

The attic has Intello holding up the insulation (see the yellow bales).  The stud wall will be a small closet, and also permits us to have a utility chase.

Next:  a little more concrete.

Doors and Windows

November 11:  Veterans’ Day, and St. Martin’s Day.

It was a tradition to sign peace treaties on St. Martin’s Day, as Martin had been a soldier-turned-monk.  Celebrations were harvest festivals preceding the cold of winter, and ending battles before winter hit makes a lot of sense.

Our battle with mud had a temporary peace, as winter’s cold froze the mud solid, making it much easier to get the machines around the house to deliver windows and doors safely.

The ground floor is glassed-in with doors and huge windows.

Here are outside views of the ground-floor installations:

Here are inside views of ground-floor installations:

Now that we’ve got window frames to see in place with concrete, we have a better idea what fits our concepts of flooring and trim materials.  The very clean lines of the clear-finished fir window frames makes for a bright contrast to the texture and color of the concrete.  We hope to play up the contrast in other finishes.

 

Below are the screws which hold the door and window frames in the concrete.

DSC_4184

Next week:  Second-floor windows, garage windows, more ventilation, plumbing, and electrical work.

Truck-in! 8 November

We’re truckin’ now! After days of waiting, things are moving fast.

Windows and doors arrived on Wednesday at about 1:30.
Original estimate was last week, secondary estimate was noon.
The address was mangled, as well as some names “corrected” to non-American spellings, so maybe the driver had a challenge in finding the site.

DSC_3908

The truck license is Minnesota.
The trailer license is from Maine.
The container hails from Barbados.
The material inside was manufactured in Germany.
The driver had a Spanish accent.
Truly, the village of our planet is involved in daily living. Our builder’s crew is locally grown, each with experience in many areas of the country and the world.

It can be tough to track the connections in a day, the paths crossed and intertwined. Sourcing materials for a life, or maybe just a house, is complicated and is inter-related with culture and economics.  (We could discuss coffee, as an example!)

The windows and doors are secured inside the container by clever framing fastened to container walls.  This prevented shifting of the materials, and requires the team to unscrewing each fastener before removing a pallet.

DSC_3938

Stemmed glasses were not in the order:
we can hardly wait to find out what is in this box.
Not a precise translation. 
VORSICHT GLAS! (beware/be wary of glass!) 
NICHT WERFEN!! (No throwing!)

The most expensive door in the whole project gets special hand-carry treatment through the mud.  Its frame follows, with a mechanical lift taking it to the back porch, and humans take it inside. There was very little space to clear the frame, and concrete does not have any give.

 

 

DSC_0030
Close-up of suction-cup tools for glass. The reflected images show 3 glass layers. 
DSC_0037
Yes, it is!

DSC_0032

Shed impediments to carrying windows and doors

Just before the container arrived, we got delivery of some insulation panels for the garage parapet.

Small, but significant side note:  electricity arrived!  The site is notably quieter, as RJStegora’s team no longer needs to run a generator.

DSC_0039

Autumn Joy Sedum continues to share its blossoms, despite the cold.

Busily Waiting

Things are getting crazy busy.  We are starting rough-in for plumbing, so suddenly we need lots plumbing fixtures on site so that the in-the-wall pieces can be installed accurately in the proper locations. But we’ve had a few snafus. The list of fixtures from our initial supplier was supplied to our plumbers about a week late, and then it was not at all accurate. So we’ve had to use plan B to obtain the things the plumbers needed first.

We’ve also been anxiously tracking the progress of our window and exterior door construction and delivery, since they’re being made in, and shipped from, Germany.  For about the past 9 days, they’ve been shipboard, crossing the Atlantic during the last 6 of those days.  We’ve been tracking the progress of “our” ship, the YM Enlightenment with the help of the MarineTraffic website.  The ship conveniently avoided Hurricane Ophelia fortunately, but it rather appears to my inexpert eye that it did have to take a less than optimal route to go around it.

As of this moment, the Enlightenment is about 10 miles off shore from Virginia Beach, heading to make port at Norfolk.  Once the container is off the ship, it will somehow get loaded on a railroad car headed towards Minneapolis.  That journey is estimated to take another 9 days  Our container of windows and doors will then be required to clear customs in a Minneapolis rail yard.  Once it does, we can get it trucked to our building site.

We very much look forward to having the house “buttoned up” with windows and doors, both to keep the weather out as well as for the security.  We’ve already had someone steal some lumber; we’d hate to have more theft occur.

Vegetable & Mineral: wood, concrete, steel.

The garage has wood rafters and decking, so more wood can be stored inside and on top.  A green roof is heavier than a typical roof, so Sweet Tree’s garage has a significant support structure.

The Electric Power box arrived!   Soon, there will be lights inside without needing the gas-powered generators. (Hint, hint, Xcel Energy, it’s your move). We’re eyeing a Power Wall, and looking for good placement for plug-in spots for future electric car charging.

I-Joists stand out from the second floor and the gable ends.  There will be insulation between them, and steel covering the second floor walls and the roof.  The steel will have a standing seam which can serve as an attachment point for solar panels.

Inside the attic space will be an office with a great view to the East.  The man standing near the window gives a sense of proportion to the space.  It should be a good size for a small office.

The great amount of concrete forming the shell of the house will be left open to see where ever possible, but the inside structure uses wood and steel to support and define the rooms.

There is a spectacular view from the attic to the ground floor, through second floor and ground floor windows.  The light from those south windows should flood the open space, and reflect up to make the attic bright as well.  We expect this to be a house of light and warmth, with windows and stairwells strategically placed for best views, illumination, and heat gain in winter.

We had a lot of rain again, and at first that produced prodigious mud ruts.
After the rain came mushrooms.

 

Topping it off and Closing the Moat

Roof decking was lifted up to the rafters, where pieces were slipped into place and secured with nails.  Once the decking is in place, the seams will be taped for air and water tightness.

This slideshow requires JavaScript.

A glycol loop runs around the base of the house.  It will help pre-heat or-cool the fresh air system, using the soil temperature from the base of the foundation. It will change very little during a year’s time, and this helps the fresh air system regulate the temperature of our home.

Bollig & Sons filled the moat in with our small mountain of soil, then packed it down.

Wood is used is so many ways in homes, even when the walls are concrete.  Floors, rafters, beams, and finished surfaces rely on wood for strength, versatility, and beauty.

 

EIFS: (Ee-fuhss) A new Acronym. Mid-September 2017

Sweet Tree Passive House is getting an Exterior Insulated Finish System (EIFS) exterior for basement, ground floor, garage, mudroom, and breezeway.  It is a layered water-proofing insulation. Sweet Tree Passive House will get a white stucco finish for the ground floor, so much of the “look” will be similar to the white of the unfinished ICF.

Here’s the progress view just before the EIFS team got started:

The house is up to the second floor, almost ready for floor joists. RJStegora places re-inforcing lumber at critical points to prevent stress on the forms. The forms are sturdy, braced and secured (and inter-laced with rebar) to withstand the impact of the heavy, wet concrete.

Here is the beginning of the EIFS installation:

The new foam layer brings the exterior out further, making for deep window sills.

Here is the second stage for the basement and garage.

The link below goes to a web site which explains EIFS systems.

http://www.eima.com/eifs

DSC_0692
Autumnal wanderer

Ground-Floor Reveal: Windows to the Future

We’ve got eyes on the future with this house, and plenty of windows to see it coming.

Revealed new concrete shows a rhythm of textures and subtle color shifts.

DSC_0078.jpg

 

Dandylions are still blooming and seeding.

The leaflet-branches all around this flower are shoots from a storm-damaged locust tree.

 

Sometimes things look different from a long view.  We won’t see the North side rooms like this after the walls go up.

DSC_0073

 

The creeping charlie makes a lovely, deep-green backdrop for a interesting boulder.